Recently the company was contracted to inspect a 6 inch, 2.5 km offshore pipeline using its InVista tool. The line had limited access on the wellhead and production platform for traditional inspection tools and had no pig traps.

In addition, the line had not been in use for approximately two-and-a-half years and the client needed to reinstate it quickly due to a planned drilling expansion. Quest Integrity was able to quickly mobilise to deliver the inspection and assessment results for the client.

Using the InVista tool, Quest Integrity overcame challenges faced in this inspection project, including no available access for a receiver and special spool arrangements to connect to the flange on the vertical section of the riser. The launcher connection was also located at an unbarred tee.

Because the tool is lightweight at 25 kg and 1,200 mm in length, temporary traps were installed in the limited space available. This meant no hot work or permanent alterations were needed. This benefit, as well as the geometry and wall-thickness data being provided in a single run, resulted in a significant cost saving for the operator.

Article continues below…

The InVista tool has superior navigational capabilities, such as short radius back-to-back bends, which also aided the ease of access (reducing the space needed for traps), unbarred off-takes and pipe schedule changes including heavy wall. The tool is bi-directional and can run in low-flow/low-pressure environments.

The total project turnaround was three days; however the actual run time was only a few hours. Due to a high tool tolerance, 99.6 per cent of wall-thickness data were collected after only two foam cleaning runs. The inspection included a fully integrated API579 compliant Level 2 fitness-for-service assessment as a standard deliverable. InVista identified the actual wall-thickness measurement as 10.3 mm (as-built drawings indicated 104.3 mm). There were also two external defects with 41 per cent wall loss and three internal corrosion points – the maximum at 25.9 per cent wall loss. In addition, three dents were identified with a maximum of 3.2 per cent of the outside diameter of the pipe.